Updates regarding the construction stages July 7th, 2022

Author July 07, 2022December 23rd, 2022

It is great to have you all with us, step by step, in the construction of the first complete suburb, Amber Forest, and to send you regular updates related to the progress of the works within the project.

Construction stage:

  • The 3 general contractors, EREN, MELSAM CONSTRUCTION and BRITT STRUCTURES, have advanced the works and currently there are 141 units in various stages of execution within the first complete, sustainable suburb in Romania.

  • The EREN company has started works on 53 villas

  • The MELSAM CONSTRUCTION company for 47 villas

  • The BRITT STRUCTURES company has started works on the first 40 apartments in the C1 and C2 buildings and on 1 more villa within the project.

Status of the authorizations:

    • Phase 1, Stage 1, 2 and 3:
      Have been obtained the building permits for 191 green homes.
    • Phase 1, Stage 4:
      At this moment, most of the urban planning certificates, as well as the necessary approvals and studies from the responsible authorities, have been obtained in order to prepare the file for the building permit. We are waiting for the approval from the Ilfov Environmental Protection Agency.
      All the documentation for obtaining the construction permit is prepared, and when the last approval from the Environmental Protection Agency is obtained, the file will be submitted to the Town Hall of the Municipality of Tunari, and we estimate that it will be obtained at the end of this summer.

The Building permits for apartments C1, C2 and C3 have been obtained.

    • Phase 2:
      The urban planning certificates have been obtained. The team of architects of the Alesonor company is working on the preparation of the necessary documentation to obtain the necessary approvals and studies from the responsible authorities, in order to prepare the file for the construction permit.